Hut 8 announced it has fully commercialized its Beacon Point AI campus by securing a second 352-megawatt IT lease, bringing the expected aggregate base-term contract value across its AI data-centre portfolio to approximately $26.6 billion. The company also reported 1,330 MW of utility capacity under construction across its major AI projects and an additional 1,300 MW of energy capacity entering exclusivity, totaling 3,180 MW in development milestones.
Hut 8's development timetable includes delivering the initial River Bend data hall in Q2 2027, Beacon Point Phase 1 in Q3 2027, and Phase 2 in Q2 2028. These commitments represent long-term contracts rather than immediate revenue, with execution dependent on power availability, construction, financing, and customer readiness.
To fund share repurchases, Hut 8 sold approximately 954 Bitcoin to buy back $74.7 million of shares during the quarter and later sold about 2,148 additional Bitcoin to repurchase another $175.3 million of shares. Post-quarter, the company increased its repurchase authorization to $1 billion. This strategy reduces treasury Bitcoin exposure while potentially increasing remaining shareholders' proportional ownership.
Additionally, Hut 8 closed a $1.07 billion senior secured revolving credit facility, providing financial flexibility though not representing immediate cash revenue.
The company’s update reflects a strategic shift from Bitcoin mining to focusing on power capacity, construction, and long-term AI tenant demand. The critical future milestones include meeting delivery targets, securing project-level financing on acceptable terms, and generating profits once sites become operational.